Dave was on site all weekend whilst Steve & Sarah spent Saturday afternoon and all day Sunday there. Dave carried out various work on brake rigging and some bodywork both on Repulse. He also looked into preparing the traction motors for lifting from the two spare bogie sets, I think the fixing bolts are proving very tough!!!
Steve & Sarah continued identifying the cut cables in Renown. The going was very slow this weekend as the cover to the water header tank level switch would not budge so in the end with help from Dave the whole level switch assembly was removed from the tank. Once the whole assembly was removed the cover was prised away to reveal the cable connections. The two level switch cables were identified and labelled. The level switch operation was tested and found to be good and therefore the whole assembly was reinstalled.
A further 2 cables was identified at the Fire Alarm Relay No1. All the cables were retested at the AWS Relay Box to prove we had identified these.
Steve and Sarah took an hour out on Sunday to meet up with John Patrick - Peak Rail Safety Officer to complete their Personal Track Safety certification.