RRRG new website top logo resized

 

Restoration diary

As one of RRRG's electrical officers I will write about my specialist field as well as general reports of work on site.

Work party report 9 January 2022

Jay, Mark and me were on site today. Mark barred the power unit intended for use in 50030 round three and a half times, added more oil and pumped it round. He also oiled the turbos we are storing for later use on this power unit again.

Jay and I carried on belling out wiring in the electrical cubicle, finding as we went, some cables where the written tags were faded to the point of being unreadable, and others where the tag had fallen off, so progress was slow while we belled those cables with visible tags, then identified the others through a process of elimination, and adding new written tags.

Membership secretary Paul Sturm
Work party report 6th March 2022

Comments

 
No comments yet
Already Registered? Login Here
Guest
Thursday, 14 November 2024

Captcha Image