Mark Burrows, Jay Hirst and I were on site today.

Mark carried on painting air filter frames, while Jay and I continued belling out cables in the electrical cubicle.

Ian the welder had been on site last week, and had fitted new grip strips to the engine room and generator compartment floors where Mark had cut out the corroded sections, as seen in my photo below. He has also started reparing around the bottom of the air filter frames opposite the electrical cubicle.