RRRG new website top logo resized

 

Restoration diary

As one of RRRG's electrical officers I will write about my specialist field as well as general reports of work on site.

Work party report 6th August 2022

​Dave Rolfe, Jay Hirst and I were on site today. Dave is continuing to paint pipework in the engine compartment, and has started to refit various filters. The first pic shows painted fuel pipework. Jay helped me finish rewiring the centre desk panel in No.1 cab. We then moved into No.2 cab to bell out the same bunch of cables. Fortunately, these had not been severed.

Reinstated fuel pipes in the engine compartment. Photo by Andy Rowlands.
The completed centre section of the driver's desk in the no 1 end cab of 50030. The wiring has now all been reinstated and bell tested. Photo by Jay Hirst.
Work party report 31st July 2022
Exhausters and blower motor lift 16th August 2022

Related Posts

Comments

 
No comments yet
Already Registered? Login Here
Guest
Thursday, 14 November 2024

Captcha Image